Wednesday, October 20, 2010

Week 4 - A skeleton emerges...

Things are really starting to move now, visited over the weekend and
expected just the beginnings of the frame to be there but found that
lot of the first floor has been put in place.
Was also surprised to see the windows here already, not sure when they
go in but they were doing a good job of holding the rain :)






Monday, October 11, 2010

Week 3 - We have a slab!

During the week we were told that the slab had been poured and were keen to get out there and check it out. Went out there on a a nice Sunday afternoon and as promised, we have concrete!!!




Our first guest

I am no builder, but I must admit it looks like they have done a very nice job...very smooth and nice edges :) So from my point of view we are off to a great start!

Wednesday, October 6, 2010

Week 2 - Pipes n holes

Well now that things have started they are moving along rather quickly....

Drains are in 

Piering hole

More piering holes

Week 1 - Site Scrape...

Well after all the trouble with rubbish its all now sorted and officially not my problem :) yay! It has begun!


Doesn't it look nice again :)